Schools for Salone Building Schools

Welcome

Projects
Building Schools
Supporting Schools
Ed Outreach
Events
Latest News
Trip Reports

Sierra Leone
Country
People
History
Civil War

About SfS
SfS Story
Board Members
Partners
Press
Fund Raising

Donate
Buy Note Cards
Buy Calendars
Special Thanks

Junctionla Primary School
Calaba Town School Painted
Calaba Town Abigail D. Butscher PrimarySchool
Opening Day March 27, 2009

Calaba Town, East End of Freetown, is one of the poorest areas around in the Freetown.  It was built after the war by the reconstruction efforts.  The community is home to many of the ethnic groups that were relocated during the war.  There was no school built for this community.  There was only the remains of an old foundation.  The only water well located for miles, was broken, and the people were forced to drink water from an unclean stream.  

Thanks to Richard Sabo's generous donation, Schools for Salone was able to begin construction of the water well in October 2008.  Schools for Salone Board Member, Michael Gibbons, visited the site before construction began.  (More about the Well.)

Another special thank you goes to the warm heart and generosity of Madieu Williams and his Foundation for funding the Abigail D. Butscher Primary School at Calaba Town. 

The Ground Breaking Ceremony was held December 16th, 2008.  Lansana Bayon, Project Manager for Masanga Children's Fund, supervised the construction, which began in January 2009 (More about the new School.).  The school was finished by early March and Opening Ceremonies were held March 27, 2009, with Schools for Salone Executive Director, Cindy Nofziger; MCF staff and Board Members and Madieu Williams attending.  (More about the Opening Ceremonies.)

The Well

Progress on the well was slow and challenging.  While hand digging to a depth of 6 meters, the workers met granite.  Workers used “fire and water” to break up the rock and then hauled the pieces out of the pit by hand.  At the end of January the water well reached a depth of 11 meters and water began to flow between the layers of rock.

Inspecting the Well Inspecting the Well
November 1, 2008

Well Complete
Protective grating blacked by
the fire and water technique
January 4, 2009
The Well The Well, before hitting rock
November 1, 2008

School walls near completion Workers use fire and water to breakup the rock
then haul it to the surface

Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player

The School

Of the December 16th Groundbreaking Ceremoney, Joseph Lamin wrote, "In Freetown, the day started with heavy pouring of rains like a raining season but we considered it as showers of blessings. The groundbreaking ceremony of Calaba town school construction started at 9:30 with representatives from the community, MCFstaff & few board members, School Agency and community police,  about fifty adults and six children attended the ceremony.  The layout of the building is  progressing and sand transportation started yesterday, and more materials will be ordered."

After the new year holiday recess, school construction resumed in early January 2009.  By January 11th, the walls had almost reached their full height.  By January 19th, the rafters were built and the walls ready for the zinc pan roof.  The roof was completed by February 3rd and the plastering of the walls began.  By February 14th, the school was painted. Steel doors and windows were used to increase security for the school. 

In early February 2009, digging for the toilets began.  Because this school is in a semi urban setting, a septic style system was built, rather than the traditional pit latrines used up country.  The entire project was finished by the end of February 2009.

School Site Foundation Ruins of original school
at Calaba Town prior to 2008

Laying out the School Laying out the School - December 16, 2008

Foundation
School Foundation Preparation

Well & School walls begun
Well and Walls begun
January 4, 2009

School walls near completion
School walls almost at full height
January 10, 2009

School walls near completion
Roof on and Plastering in process
February 2, 2009

Digging Latrine
Latrine digging begins
February 2, 2009

Well ready to cap
Well lined and ready to cap
March 6, 2009

Back drainage ditches for rainy season
Rainy Season drainage at back of School
March 6, 2009
Michael Gibbons visits the site SfS Board Member, Michael Gibbons,
visits the site November 1, 2008

Groundbreaking Ceremony Groundbreaking Ceremony
with Fatmata Kargbo, MCF Board Member
December 16, 2008

Making Bricks
Making Bricks by Hand

Lansana & school under construction
MCF Project Manager, Lansana Bayon,
at school site January 4, 2009

Walls almost ready for roof
Walls almost ready for roof rafters
January 10, 2009

School walls near completion
Roof on and the plastering in process
Rocks pile up from the well
February 2, 2009

School walls near completion
Roof, front walk and steps

Latrines complete
Latrines completed
March 6, 2009

Calaba Town School nearing completion
Nearing completion
March 6, 2009

You can help build a promising future for SierraLeone's children.